Skip to content Skip to footer

How the NRC Brass Refuses to Recognize Costly Lessons of Fukushima

The Nuclear Regulatory Commission issued a report that contained a surprising conclusion.

On March 11, 2011, a 9.0 earthquake and 45-foot-high tsunami overwhelmed the emergency cooling systems at the Fukushima Dai-ichi nuclear complex on Japan’s eastern coast. Meltdowns occurred in units 1, 2 and 3, and the unit 4 containment building was severely damaged, leaving 460 tons of spent fuel stored atop the building at risk of collapse. One-third of Fukushima Prefecture (eight percent of Japan’s land mass) and 1.5 million people were affected by fallout. The region’s $3.2 billion agricultural sector was wiped out.

In the months following the multiple meltdowns, the Nuclear Regulatory Commission (NRC) formed a Near-Term Task Force (NTTF) to recommend protective countermeasures. The explosive demise of Fukushima’s reactors had drawn special attention in the United States owing to a singular, alarming fact: The reactors that failed in Japan were built by General Electric, and 23 similar Mark I reactors were in operation at 16 sites in 12 US states. In addition, another eight Mark 2 reactors with similar design problems are located at five sites in four states.

On July 12, 2011, the NTTF issued a 96-page report titled “Recommendations for Enhancing Reactor Safety in the 21st Century: Review of Insights from the Fukushima Dai-ichi Accident” containing 12 “overarching recommendations.” Most were vague calls to “evaluate potential enhancements,” and “strengthen . . . mitigation capabilities,” and “identify insights.” There was, however, one concrete recommendation. It called for “requiring reliable hardened vent designs . . . [on all] Mark I and Mark II containments.”

In internal memos, NRC staff warned that safety improvements were essential for “Mark I or Mark II containments to address specific design concerns (e.g., high conditional containment failure probability given a core melt) that could result in “releases of radioactive materials, hydrogen, and steam into the reactor building.” The addition of Hardened Containment Vents (HCVs) would allow reactor operators to release high-temperature and high-pressure gasses to the atmosphere, which could prevent reactor core damage that could generate dangerous accumulations of explosive hydrogen gas.

NRC: “It Can’t Happen Here”

On the first anniversary of the Fukushima quake, the NRC issued a report that contained a surprising conclusion. The NRC ruled that a “sequence of events such as the Fukushima Dai-ichi accident is unlikely to occur in the US. Therefore, continued licensing activities [of US reactors] do not pose an imminent threat to public health and safety.”

The NRC investigation clearly identified the failure of pressure vents on Japan’s reactors as a major contributing cause of the meltdowns and explosions. Although the NRC acknowledged that the importance of HCV systems was “well established,” the NRC noted that HCVs currently were “not required” on Fukushima-style rectors in the US. Moreover, at those US sites where HCVs had been voluntarily installed, “a wide variance exists with regard to . . . reliability.”

To address this critical safety lapse, the NRC has proposed that all Mark I and Mark II reactors be equipped with vents sufficiently “hardened” to work during an accident. But, as Fukushima demonstrated, even hardened venting systems can fail if they rely on electricity or air pressure that could be lost during an accident. Hence, the NRC has required that new HCV systems also must also be “reliable” – i.e., designed to operate even during a station blackout “to ensure . . . adequate protection of public health and safety.” US operators were given until February 28, 2013, to submit plans on how they intend to implement safety upgrades.

Japan’s New Safeguards

In January 2013, Japan’s Nuclear Regulatory Authority announced the imposition of three new safety measures for all of the country’s existing reactors. These included:

1. “Power supply vehicles” capable of providing additional emergency power for seven days in the event of a loss of outside electric power.

2. Filters on emergency vents capable of reducing the radiation emitted in the event of an accident.

3. Creation of “secondary control rooms” built at a safe distance from operating reactors. In the event of an accident, these fallback control rooms would allow operators to safely attempt to cool reactor cores, and, if needed, vent steam and radioactive gases into the atmosphere. (Germany and Switzerland already have such systems; the United States does not.)

Japan’s latest post-Fukushima guidelines also call for expanding evacuation zones surrounding damaged reactors from 5 to 30 kilometers (3 to 18 miles).

The NRC’s mandatory evacuation zone inside the United States is limited to 10 miles. During the Fukushima meltdowns, however, the State Department urged US citizens living in Japan to relocate at least 50 miles from the damaged reactors.

Lessons Learned?

To date, the NRC’s Lessons Learned Task Force has only proposed adopting one of Japan’s post-Fukushima safeguards – the installation of HCVs with radiation filters – but even this decision has come under fire. In January 2013, a phalanx of 21 pro-nuclear Republicans who serve on the House Energy and Commerce Committee signed a letter calling on the NRC to quash the radiation-filtering recommendation as too burdensome for the beleaguered nuclear industry. The industry fears the cost of installing external radiation filters could lead to the shutdown of many older US plants. (Three of the Congressional letter-signers come from states where a total of five Fukushima-style GE reactors were recently found to be at increased risk of damage due to earthquakes.)

While Japan has called for swift action to address these three critical protective measures, the NRC has indicated that the deadline for action on its single safety improvement, the installation of HCVs (currently set to be accomplished by December 31, 2016), may be pushed back to December 31, 2017.

In an Order to Modify Licenses alert sent to US reactor operators on March 12, 2012, the NRC expressed concern that the Fukushima disaster had shown how “extreme natural phenomena could challenge . . . prevention, mitigation and emergency preparedness.” In response, the NRC ordered the operators of 20 US reactors to “implement requirements for reliable hardened containment vents at their facilities.” (The NRC actually ordered such improvements in 1989, but it turned out the vents needed electrical power and air pressure to operate, and, in the event of an accident, electricity and air pressure could be lost.)

A Thirty-Year Delay

In its March 29, 2012, NUREG-1150 report on Severe Accident Risks, the NRC concluded that “the Mark I and Mark II containments do not have the same margins of safety that other containments . . . have during accidents.” This report went on to state: “The NRC and nuclear industry have recognized the potential need to vent Mark I and Mark II containment designs to cope with severe accident conditions since at least the early 1980s.” [Emphasis added.]

So why didn’t the NRC act sooner? It was a cost-benefit decision. The commission ruled that the expense of the making the upgrades was not warranted due to the “low probability” of a nuclear accident. In a report dated November 26, 2012, NRC staff noted that “legislators and regulators in other countries did impose requirements in the aftermath of the accidents at Three Mile Island and Chernobyl,” clearly choosing “the defense-in-depth argument . . . with less or no consideration of cost/benefit analyses.” Still, the NRC was not swayed.

In a November 26, 2012 report, “Policy Issue Notation Vote,” the NRC staff offered four options to the commissioners:

1. Continue with planned addition of “reliable hardened vents.”

2. Upgrade safety with “severe accident capable vents.”

3. Design and install “engineered filtered containment venting” to block the release of radioactive clouds following an accident.

4. Consider additional strategies to handle “severe accident confinement.”

The staff concluded both options 2 and 3 were “cost-justified in light of the substantial increase in the overall protection of the public health and safety” and recommended option 3. Neither of the two improvements will come cheap. The cost for installing Severe Accident Capable Venting Systems was estimated at $3,027,000 per reactor while the estimated unit cost to install Engineered Filtered Venting Systems totaled $16,127,000.

The Industry Pushes Back

The Nuclear Energy Institute (NEI) and plant operators countered that expensive filters are “unnecessary” and that merely “hardening” the venting systems should suffice. The Electric Power Research Institute’s (EPRI) argument against installing radiation filters was particularly wishful. “The best way to avoid radiological release and potential land contamination,” EPRI argued, was to “prevent an accident from occurring.” The NRC’s Advisory Committee on Reactor Safeguards initially sided with industry’s call for “performance-based standards,” but NRC staff argued this approach would delay action by several years, thereby violating the commission’s commitment to address the filtering issue “without delay.”

Noting that filtering technologies already exist and “have been demonstrated through significant testing and application at nuclear power plants worldwide,” the staff identified evaluation of filter vents as a “Tier 1 issue” — i.e., an action “to be initiated without unnecessary delay.”

The NRC’s Tier 1 actions include: “evaluations” of flood and earthquake hazards; improved station blackout (SBO) regulations; strategies for addressing “beyond-design-basis events” (i.e., unplanned-for disasters); hardened vents for Mark I and Mark II containments; and installing instruments to monitor the stability of spent fuel storage pools.

The NRC’s Tier 2 concerns (i.e. those requiring “further technical assessment and alignment”) include: spent-fuel pool safety and evaluating the danger from hurricanes, floods and other extreme weather events.

The Tier 3 recommendations (“actions that require further staff study to support a regulatory action”) include: “enhancements” to protect reactors from fires and floods triggered by earthquakes; requiring HCVs for other at-risk reactor designs; developing strategies to prevent or “mitigate” buildups of explosive hydrogen inside containment structures; improvements in handling a “prolonged station blackout and multiunit events,” and providing staff training on how to deal with “severe accidents.”

Nuclear Watchdogs Challenge NRC to Act

Citizens groups and nuclear watchdogs recently urged the NRC to implement additional post-Fukushima safety measures, but the commission seems determined to move slowly on a small number of focused changes.

On January 31, 2013, the Nuclear Information Resource Service (NIRS) and other organizations submitted a citizens’ petition demanding that the NRC and the Federal Emergency Management Agency (FEMA) address a number of additional changes. These include:

1. Expanding the 10-mile “emergency planning zone” to include a 25-mile “plume emergency zone,” a 50-mile Emergency Response Zone, and a 100-mile “ingestion pathway zone.”

2. Update emergency response and evacuation plans to incorporate the increased dangers posed by climate change – i.e., droughts, hurricanes, tornadoes and flooding.

3. Base emergency planning on real-life experiences (i.e., TMI, Chernobyl, Fukushima) and not simply on computer simulations.

4. Acknowledge the National Academy of Science finding that “there is no safe dose of radiation” and increase protection levels for people threatened by long-term and sustained exposures. (Because women and children are most at risk, federal radiation guidelines should no longer be based on the anticipated risk to “the average man.” The preferred guidelines should, instead, be based on the risks posed to a young girl.)

5. Emergency supplies of potassium iodine tablets should be made widely available to protect populations against the risk of thyroid cancer, disease and mental retardation that can result from breathing and ingesting fallout byproducts.

6. Establish “best practices” to determine whether “shelter-in-place” or “evacuation” poses the best response to a nuclear power plant accident.

It is now up to the NRC’s five commissioners to decide whether to order operators to install safety improvements that could cost tens of millions of dollars per reactor. The commissioners could insist on swift implementation or they could simply ask for “further study.”

Unfortunately, as the website Beyond Nuclear notes, “the controversial and expensive ‘fix’ for the unreliable, aging and failing GE designs has clearly politicized the commissioner’s’ upcoming vote.”

Join us in defending the truth before it’s too late

The future of independent journalism is uncertain, and the consequences of losing it are too grave to ignore. To ensure Truthout remains safe, strong, and free, we need to raise $22,000 by the end of today. Every dollar raised goes directly toward the costs of producing news you can trust.

Please give what you can — because by supporting us with a tax-deductible donation, you’re not just preserving a source of news, you’re helping to safeguard what’s left of our democracy.